Pine Island Early Learning Center Construction Updates

Kraus-Anderson (KA) will begin construction on a new project for the Pine Island School District - ISD 255. Designed by Wendell Architects, the $6.8 million dollar project is a new (2 Level) 20,356 square foot Early Childhood Facility. The project consists of precast walls & plank, storefront systems, 2,000 SF multipurpose area that also acts as a storm shelter, office/classroom spaces, 2-stop elevator and second level indoor playground

Construction Activities:

Work in August:

  • Interior Mechanical, Electrical, and Plumbing Rough-Ins are going in
  • Roofing is “water tight” allowing drywall to get started
  • Windows are being installed
  • Exterior grading is wrapping up
  • Site curbing and asphalt were completed in the month of August

Upcoming Work in September:

  • Continuing Finishes and working towards the lower level
  • MEP rough-ins are moving down to the lower level
  • Windows will be completed in late September into early October
  • Metal Panel field measuring will occur and installation will begin the beginning of October

Time Lapse Video

Photos:

August 2022
July 2022
June 2022
May 2022
April 2022

Weather:

Construction days lost to weather this month: 0

Total construction days lost to weather: 8

Safety:

Lost time days: 0

Days worked without lost time accident: 5.5 Months

Dan Kjellberg | Project Manager

Troy Dale | Project Superintendent

Silvia Magana | Senior Project Coordinator

Dan Goemann | Architect

Nickisha Vander Wyst | Architect